Officials told to address funding and other bottlenecks; teaching hospital and liver transplant projects to undergo separate reviews
NASEERABAD (6 AM Report) : Commissioner Naseerabad Division Salahuddin Noorzai has directed officials to ensure timely and quality completion of the Naseerabad Medical College, warning that negligence or unnecessary delays in the project will not be tolerated.
Chairing a review meeting on the under-construction medical college, the commissioner said funding and other bottlenecks identified during the meeting should be taken up with the relevant authorities for early resolution.
Deputy Commissioner Naseerabad Varender Lal, Engineer Mir Muhammad Mengal and other officials attended the meeting.
Medical College Project Comprises Three Phases
Project Director Engineer Amir Aziz Magsi briefed the meeting that the medical college project comprises three phases, including construction of the main building and other components. He said funding constraints and other issues needed timely resolution to prevent delays in construction.
Noorzai said the medical college was an important project for the entire Naseerabad Division and would contribute to improving medical education and healthcare facilities in the region.
The meeting was also informed that a teaching hospital and liver transplant project are linked to the initiative. Separate meetings will be scheduled to review their progress and related matters in detail.
The commissioner directed officials to closely monitor construction quality and progress and ensure that all possible measures are taken to remove obstacles and expedite completion of the project.