Prior NOC mandatory for government, semi-government and private entities; violations may invite criminal and contempt proceedings, asphaltic base course completed on 14.5km of Sariab Service Road, drainage work 85pc complete
QUETTA (6 AM Report): The Balochistan High Court has barred unauthorized excavation of newly constructed roads, footpaths and other urban infrastructure in Quetta, directing that prior permission and a No Objection Certificate (NOC) must be obtained for utility or other works and warning that violations could result in criminal as well as contempt proceedings.
BHC Bench Reviews Quetta Development Projects
A two-member bench comprising Chief Justice Balochistan High Court Justice Muhammad Kamran Khan Mulakhail and Justice Muhammad Najmuddin Mengal issued the directions while hearing a constitutional petition concerning ongoing development projects in Quetta, particularly the Sariab Service Road and storm-water drainage system.
Additional Advocate General Balochistan Zahoor Ahmed Baloch, Additional Attorney General Muhammad Fareed Dogar, Project Director of the Chief Minister’s Package for Quetta Development Muhammad Rafiq and other relevant officials appeared before the court.
The Project Director submitted a progress report on the Sariab Service Road and storm-water drainage works, informing the court that the asphaltic base course had been completed on 14,500 meters of the 15,140-metre service road, with work remaining at locations where obstructions persisted.
According to the report, the asphaltic wearing course had been completed on approximately 6,500 meters of the road, construction of the bridge had been completed and around 85 per cent of the storm-water drain work had been finished. Installation of curbstones and pavers was about 30 per cent complete.
Unauthorized Excavation Allegedly Damages Newly Built Road
The court was informed that unidentified individuals associated with certain cable and communication companies had excavated portions of the newly constructed Sariab Service Road without permission from the relevant authorities, allegedly damaging the road and public infrastructure and affecting ongoing development work.
A letter sent by the Project Director to the SP Sariab on August 20 regarding the matter was placed before the court, along with correspondence dated February 13 concerning the relocation of utilities.
The bench observed that newly constructed roads, footpaths and other infrastructure could not be allowed to suffer repeated damage through unnecessary or unauthorized excavation.
The court directed that the Project Director must be informed and formal permission obtained before any fresh excavation or utility work. Where a utility corridor was available, it should be used, while any necessary work should be carried out at a location identified by the Project Director to prevent damage to newly constructed roads, footpaths and pavers.
DC Quetta Directed to Act Against Unauthorized Digging
The bench directed the Deputy Commissioner Quetta to ensure prompt action in accordance with law against those responsible whenever the Project Director reported unauthorized excavation or violation of the court’s directions.
The court also directed the office of the Additional Advocate General to inform all government, semi-government and private companies that obtaining an NOC from the Project Director would be mandatory before undertaking any work in already developed areas.
The bench made it clear that violations could result in criminal proceedings against those responsible, while non-compliance with the court’s directions could, where appropriate, also invite contempt proceedings.
During the hearing, Advocate Attaullah Langove also filed CMA No. 3504/2026. A copy was provided to the Additional Advocate General, who was granted time to examine it.
The court directed that copies of its order be forwarded to the relevant authorities through the offices of the Additional Attorney General Balochistan and Advocate General Balochistan for information and compliance.