QUETTA (6 AM Report): The Quetta Electric Supply Company (QESCO) has announced that electricity supply will remain disrupted across Quetta and other parts of Balochistan due to scheduled maintenance and installation work on the 220kV Sibi–Quetta transmission line by the National Grid Company (NGC).
Maintenance Scheduled for July 28–29
According to a QESCO statement, the maintenance work will be carried out on July 28 and 29, with the transmission line remaining out of service from 7:00 a.m. to 5:00 p.m. on both days.
QESCO said the shutdown of the transmission line is expected to create a power shortfall of approximately 220 megawatts, which will be managed through load management across the province.
The utility said the additional power deficit will be addressed through scheduled load management affecting Quetta and other areas of Balochistan during the maintenance period.
Consumers Asked to Cooperate
QESCO apologized for the temporary inconvenience and appealed to consumers for their cooperation while the maintenance and installation work is completed.