ZKB commits to completing key road project within two-and-a-half months; machinery and workforce to be increased as Commissioner orders removal of bottlenecks, strict monitoring of construction standards
BARKHAN/RAKHNI (6 AM Report), Aug 20: Commissioner Koh-e-Suleman Division Mujeeb-ur-Rehman Qambrani has directed the contractor and relevant authorities to accelerate work on the Rakhni-Bekar Highway, as ZKB committed to completing the key road project within the next two-and-a-half months by deploying additional machinery and manpower.
The Commissioner made it clear that while the pace of construction must be increased, no compromise on quality would be tolerated, stressing that the highway was vital for improving regional connectivity, facilitating safer travel and boosting trade and economic activity.
Qambrani issued the directives during a meeting with ZKB company owner Haji Mohabbat Khan, XEN B&R North Dera Bugti Shams-ul-Haq and other relevant officials. Additional Commissioner Abdul Basit Buzdar was also present.
Construction Progress and Completion Timeline Reviewed
The meeting reviewed progress on the Rakhni-Bekar Highway and other ongoing development schemes, focusing on the pace of construction, progress on different sections, quality standards, availability of machinery and manpower, and the targeted completion timeline.
Officials briefed the Commissioner on construction activities and progress achieved so far.
ZKB owner Haji Mohabbat Khan assured the Commissioner that construction activities would be further accelerated to complete the Rakhni-Bekar road project within the next two-and-a-half months.
He said the company was increasing machinery and manpower at the project site to speed up work and meet the committed deadline.
Commissioner Qambrani directed the contractor and concerned authorities to immediately remove bottlenecks affecting construction and ensure better coordination so that the project could be completed without unnecessary delay.
He said Chief Minister Balochistan Mir Sarfraz Bugti and the provincial government had a clear policy that public development projects should be completed within stipulated timelines and according to prescribed quality standards.
Project Delays Deprive Communities of Development Benefits
The Commissioner said delays in development projects not only caused hardship for residents but also prevented communities from receiving their intended social and economic benefits on time.
He said completion of the highway would strengthen connectivity between remote areas, provide safer and more efficient travel and facilitate trade, business and other economic activities in the region.
Qambrani said the pace and quality of construction would remain under continuous monitoring to ensure that the Rakhni-Bekar Highway was completed within the committed timeframe and provided residents with a durable and reliable transport link.